On Monday morning a certain machine ran continuously at a uniform rate to fill a production order. At what time did it completely fill the order that morning?
(1) The machine began filling the order at 9:30 a.m.
(2) The machine had filled $$\frac{1}{2}$$ of the order by 5 10:30 a.m. and $$\frac{5}{6}$$ of the order by 11:10 a.m.