A project scheduled to be carried out over a single fiscal year has a budget of $12,600, divided into 12 equal monthly allocations. At the end of the fourth month of that fiscal year, the total amount actually spent on the project was $4,580. By how much was the project over its budget?
-
A$ 380
-
B$ 540
-
C$1,050
-
D$1,380
-
E$1,430